The construction of a wastewater pumping station in Kielce, Poland

The scope of work included the complete execution of one of the largest wastewater pumping station in Kielce, Poland.

We installed storage reservoirs KWH PIPE 5 pcs x 32 m3, pumping stations with a capacity of 6 m3/min, 3 separators and 15 wells.

The project also included:
– installation of water line (170 m) made of cast-iron pipes DN 110 Saint-Gobain
– installation of sewer DN 300 PEHD
– land development: concrete fence, green areas, road, footways

The project was extremely difficult due to the high level of ground water, most of the work was carried out using an wellpoints.

The project deadline was six months.